Tuesday 21 August 2012

Some plumbing done, Bricks arrive, Laying today!

The lions share of plumbing was completed on Friday 17/8. Pictures below.

On Monday 20/8, the bricks arrived. I've heard that they only deliver enough for one floor at a time, so we'll see.

On Tuesday 21/8, the bricks are being laid. This process should take around 1 week.

Cement delivery and balcony nearly complete!


Plumbing in d/s bathroom going to garage space, and overhead plumbing for upstairs -



Some plumbing for upstairs.


Some more downstairs shots, the right one is the outside shower -



main bathroom plumbing u/s and overhead plumbing d/s


More upstairs plumbing -

rear tap and rear external shower (for pool)


fittings for the gas water heater -


gas water heater provision and the gas run -


more gas run, note the artful bending of pipe - love copper work!

piping goes to front for connection to gas mains (I believe!) -


this is where the water comes into the house, and flies off to front tap -


u/s plumbing in ensuite -


u/s plumbing in main bathroom -

more u/s plumbing


one more ceiling shot, great room ceiling -

And here's a photo from lunchtime today. The brickies are down the back. I didn't dare go in...

I learnt that the ground level roof was completed yesterday, as shown in the 2nd photo below.




No comments:

Post a Comment

Hi! Thanks for your comment!

It has been forwarded to the site administrator for approval.

If it isn't spam, it will be published, unless you've requested otherwise.

Thanks for contributing to the site!